Construction of MHP Sumalata [ 2010 ]

MHP Sumalata is utilizing a potential power of Mata-Putih river. Design parameter of MHP Sumalata is as the followings:

 

- Design Head       : 7.6 m

- Design Flow        : 300 lt/s

- Rated power       : 15 kW

 

Because of low head, the MHP Sumalata is designed using the propeller turbine. Additionally, the distance from powerhouse to the BTS site is 5.5 km. Therefore, the electricity is transmitted through a medium voltage of 20 kV